Projects Frontend Portlet

embedded = false isPreview = false
  • SELECTED 2026

Leça Green Corridor

Matosinhos (Portugal), 2024

The Corridor stretches for 48 kilometres and connects four municipalities, providing 22 hectares of linear public space as an important landscape infrastructure for environmental regeneration, water resilience and sustainable mobility.

Previous state

The Leça River Valley has traces of settlements dating back to the Palaeolithic period but the present-day landscape clearly reflected the pressures of human presence in unregulated sprawl combining residences, industrial estates, farmlands, and woods, all criss-crossed by motorways and railway lines. Pollution and asphalt had damaged the zone, even though it still retained a historical and cultural heritage of great value that was worth recovering.

Aim of the intervention

The project planned to create an extensive green corridor of some forty kilometres running alongside the river to connect with the metropolitan area of Porto and make the area more resilient to climate change. Rather than an aggressive, large-scale intervention, natural solutions were applied, among them regenerating riparian forests, decontaminating soil, and sustainable management of rainwater. Another major challenge was offering an alternative to cars in order to improve everyday mobility, and this part of the project was carried out in close consultation with local residents, experts, and municipal administrations.

Description

In order to make the work possible, private land was purchased and the tasks of cleaning water and soil began. The riverbanks were strengthened with native plants and vegetation able to absorb contamination and prevent landslides when the river floods. As for mobility, a continuous four-metre-wide path for pedestrians and cyclists was opened, connecting directly with public transport lines and urban centres. The route was completed with footbridges for crossing the river and adaptation of pre-existing bridges to ensure fluid, uninterrupted movement.

Assessment

The green belt has now connected mountain and sea, returning to residents a once degraded space. Today, the path has been incorporated into the routine of many people who use it to travel to and from work, and to take a lunchtime break with colleagues. At weekends it is now a gathering place for people doing sport or walking, and for family picnics. Moreover, talks, school visits, and sessions of volunteer work of cleaning the river and planting trees have given the community a renewed sense that this natural environment is theirs to enjoy.


[Last update: 05/10/2026]

Technical sheet

CITY: Matosinhos
COUNTRY: Portugal
BEGINNING OF THE PROJECT: 2017
BEGINNING OF WORK: 2021
END OF WORK: 2024
PROJECT MANAGEMENT: Câmara Municipal de Matosinhos | Câmara Municipal da Maia
CONSTRUCTOR: Extraco | Tecnifeira | Cebrial
AREA: 22,000 m²
COST: 10,000,000 €

Credits

DEVELOPER:
Câmara Municipal de Matosinhos, Câmara Municipal da Maia

AUTHORS:
Laura Roldão LR


Related documents