  • The north façade of the library.<br />
    Open-Air-Library
    Magdeburg [Germany] 2009
    JOINT WINNER
     

    BEGINING YEAR: 2005

    BEGINING OF WORK YEAR: 2008

    COST: 325,000 €

    AREA: 488 m2

    AUTHORS:

    KARO* with Architektur+Netzwerk

    DEVELOPER:

    Department of Building and Construction, Bürgerverein Salbke-Fermersleben-Westerhüsen e.V.

  • <br />
    Den Norske Opera & Ballett
    Oslo [Norway] 2008
    JOINT WINNER
     

    BEGINING YEAR: 2000

    BEGINING OF WORK YEAR: 2003

    COST: 500,000,000 €

    AREA: 38,500 m2

    AUTHORS:

    SNØHETTA

    DEVELOPER:

    STATSBYGG

  • <br />
    Urban Activators: theater podium & brug Grotekerkplein
    Rotterdam [Netherlands] 2009
    SPECIAL MENTION
     

    BEGINING YEAR: 2005

    BEGINING OF WORK YEAR: 2008

    COST: 1,033,800 €

    AREA: 200 m2

    AUTHORS:

    Atelier Kempe Thill architecs and planners

    DEVELOPER:

    Rotary Club Rotterdam Noord, foundation 'Grotekerkplein', OBR Rotterdam

  • <br />
    Paseo Marítimo de la Playa Poniente
    Benidorm [Spain] 2009
    SPECIAL MENTION
     

    BEGINING YEAR: 2002

    BEGINING OF WORK YEAR: 2006

    COST: 10,620,000 €

    AREA: 40,000 m2

    AUTHORS:

    Office of Architecture in Barcelona

    DEVELOPER:

    Generalitat Valenciana - Ayuntament de Benidorm

  • <br />
    Passage 56 / espace culturel écologique
    Paris [France] 2009
    SPECIAL MENTION
     

    BEGINING YEAR: 2006

    BEGINING OF WORK YEAR: 2007

    COST: 90,000 €

    AREA: 200 m2

    DEVELOPER:

    atelier d'architecture autogérée

    AUTHORS:

    atelier d'architecture autogérée

  • <br />
    Casetas de pescadores en el puerto
    Cangas do Morrazo [Spain] 2008
    SPECIAL MENTION
     

    BEGINING YEAR: 2003

    BEGINING OF WORK YEAR: 2005

    COST: 1,200,000 €

    AREA: 3,920 m2

    AUTHORS:

    Irisarri + Piñera

    DEVELOPER:

    Puertos de Galicia

  • View of the Y-shaped footbridge.<br />
    MadridRío
    Madrid [Spain] 2009
    FINALIST
     

    BEGINING YEAR: 2005

    BEGINING OF WORK YEAR: 2008

    COST: 350,000,000 €

    AREA: 1,100,000 m2

    AUTHORS:

    Burgos Rubio Garrido Porras y Lacasta

    DEVELOPER:

    Coordinacion General de Proyectos Singulares, Ayuntamiento de Madrid

  • The uses and senses of insipid, run-down spaces significantly intensify through the holding of collective events such as the opera season in the Eichbaum station.<br />
    Eichbaumoper
    Mülheim an der Ruhr [Germany] 2009
    FINALIST
     

    BEGINING YEAR: 2006

    BEGINING OF WORK YEAR: 2008

    COST: 420,000 €

    AREA: 1,000 m2

    AUTHORS:

    Raumlaborberlin

    DEVELOPER:

    raumlaborberlin

  •  Broken up by the roots of trees, the steps of the stairway have been left as they were but a parallel stairway has been built beside it to obey the same rhythm of the stairway sections and landings.
    Ulap-Platz
    Berlin [Germany] 2008
    FINALIST
     

    BEGINING YEAR: 2005

    BEGINING OF WORK YEAR: 2007

    COST: 1,100,000 €

    AREA: 13,000 m2

    AUTHORS:

    Till Rehwaldt

    DEVELOPER:

    Abt. Städtebau und Projekte, Hauptstadtreferat, Berlin

  • After the intervention, the 530 square metres of the block of land have been turned into a new public square with a metal structure over fifteen metres high which is the support of a hanging garden.<br />
    Jardín vertical y plaza pública Delicias
    Zaragoza [Spain] 2008
    FINALIST
     

    BEGINING YEAR: 2002

    BEGINING OF WORK YEAR: 2007

    COST: 1,319,000 €

    AREA: 1,786 m2

    AUTHORS:

    Sicilia y Asociados

    DEVELOPER:

    Asociación de Vecinos Delicias "Manuel Viola"

  • <br />
    Jardí del Museu Can Framis
    Barcelona [Spain] 2009
    FINALIST
     

    BEGINING YEAR: 2007

    BEGINING OF WORK YEAR: 2008

    COST: 7,354,000 €

    AUTHORS:

    Badia i Rodríguez

    DEVELOPER:

    FUNDACIÓ VILA CASAS. LAYETANA

  • The sinuous s-shaped curves of the bridge rest, at three points, on pairs of angled metal piers wedged in the form of a V.<br />
    Riverside Masterplan
    Castleford [United Kingdom] 2008
    FINALIST
     

    BEGINING YEAR: 2003

    BEGINING OF WORK YEAR: 2006

    COST: 3,650,000 €

    AREA: 2,734 m2

    AUTHORS:

    McDowell+Benedetti

    DEVELOPER:

    City of Wakefield Metropolitan District Council

  • Conversion of an esplanade once used as an open-air car park into a representative and versatile square that can be used as venue for large-scale events.<br />
    Vabaduse väljak
    Tallinn [Estonia] 2009
    FINALIST
     

    BEGINING YEAR: 1998

    BEGINING OF WORK YEAR: 2008

    COST: 20,000,000 €

    AREA: 11,000 m2

    AUTHORS:

    Andres Alver, Veljo Kaasik, Tiit Trummal

    DEVELOPER:

    Tallinn City Government

  •  

    BEGINING YEAR: 2000

    BEGINING OF WORK YEAR: 2002

    COST: 78,000,000 €

    AREA: 420,000 m2

    AUTHORS:

    Atelier Corajoud

    DEVELOPER:

    Communauté Urbaine de Bordeaux

  • <br />
    Campus des Comtes de Champagne
    Troyes [France] 2009
    FINALIST
     

    BEGINING YEAR: 2003

    BEGINING OF WORK YEAR: 2007

    COST: 26,848,700 €

    AREA: 10,973 m2

    AUTHORS:

    intégral Lipsky+Rollet architectes

    DEVELOPER:

    Communauté du Grand Troyes

  • <br />
    Lanternen/ Norwegian Wood
    Sandnes [Norway] 2008
    FINALIST
     

    BEGINING YEAR: 2006

    BEGINING OF WORK YEAR: 2008

    COST: 1,400,000 €

    AREA: 2,500 m2

    AUTHORS:

    AWP+ Atelier Oslo

    DEVELOPER:

    Sandnes Kommune, Norwegian wood steering group

  • <br />
    Rehabilitación de la Alameda de Hércules
    Sevilla [Spain] 2009
    FINALIST
     

    BEGINING YEAR: 2005

    BEGINING OF WORK YEAR: 2007

    COST: 11,934 €

    AREA: 38 m2

    AUTHORS:

    José Antonio Martínez Lapeña, Elías Torres Tur, arquitectos

    DEVELOPER:

    Gerencia de Urbanismo del Ayuntamiento de Sevilla

  • <br />
    Entre catedrales
    Cádiz [Spain] 2009
    FINALIST
     

    BEGINING YEAR: 2006

    BEGINING OF WORK YEAR: 2008

    COST: 1,500,000 €

    AREA: 1,000 m2

    AUTHORS:

    Alberto Campo Baeza

    DEVELOPER:

    Ayuntamiento de Cádiz

  • <br />
    Remodelación del puerto
    Malpica de Bergantiños [Spain] 2009
    FINALIST
     

    BEGINING YEAR: 2005

    BEGINING OF WORK YEAR: 2008

    COST: 2,843,240 €

    AREA: 13,710 m2

    AUTHORS:

    Creus e Carrasco arquitectos

    DEVELOPER:

    Xunta de Galicia, Ente Público Portos de Galicia

  • <br />
    Furtwänglergarten
    Salzburg [Austria] 2009
    FINALIST
     

    BEGINING YEAR: 2007

    BEGINING OF WORK YEAR: 2008

    COST: 900,000 €

    AREA: 5,000 m2

    AUTHORS:

    Auböck + Kárász

    DEVELOPER:

    Municipality of Salzburg

  • <br />
    NLA Skywalk
    London [United Kingdom] 2008
    FINALIST
     

    BEGINING YEAR: 2008

    BEGINING OF WORK YEAR: 2008

    COST: 55,200 €

    AREA: 280 m2

    AUTHORS:

    Carmody Groarke

    DEVELOPER:

    New London Architecture / London Festival of Architecture

  •  

    BEGINING YEAR: 2001

    BEGINING OF WORK YEAR: 2004

    COST: 6,500,000 €

    AREA: 11,950 m2

    AUTHORS:

    Schaller/Theodor Architekten BDA

    DEVELOPER:

    Stadt Köln, Amt für Stadtentwicklung und Statistik

  • <br />
    Redesign of main square
    Maria Saal [Austria] 2008
    FINALIST
     

    BEGINING YEAR: 2002

    BEGINING OF WORK YEAR: 2007

    COST: 1,200,000 €

    AREA: 2,250 m2

    AUTHORS:

    nonconform architektur vor ort

    DEVELOPER:

    Maria Saal Beteiligungs und Infrastruktur GmbH

  • <br />
    Parque Verde do Mondego
    Coimbra [Portugal] 2008
    FINALIST
     

    BEGINING YEAR: 1995

    BEGINING OF WORK YEAR: 1997

    COST: 18,250,000 €

    AREA: 230,000 m2

    AUTHORS:

    MVCC - Mercês Vieira e Camilo Cortesão

    DEVELOPER:

    Câmara Municipal de Coimbra

  • <br />
    Paisatgisme de la línia 1 del TRAM
    Alacant [Spain] 2009
    FINALIST
     

    BEGINING YEAR: 2005

    BEGINING OF WORK YEAR: 2006

    COST: 5,200,000 €

    AREA: 12,000 m2

    DEVELOPER:

    Ente Gestor de la Red de Transporte y de Puertos de la Generalitat. Consellería de Infraestructuras y Transporte

    AUTHORS:

    Eduardo de Miguel, José María Urzelai

  • <br />
    Square and open air altar
    Radovlijca [Slovenia] 2008
    FINALIST
     

    BEGINING YEAR: 2005

    BEGINING OF WORK YEAR: 2005

    COST: 478,000 €

    AREA: 1,790 m2

    AUTHORS:

    Zorec, Tepina

    DEVELOPER:

    Franciscan monastery Brezje

  •  

    BEGINING YEAR: 2005

    BEGINING OF WORK YEAR: 2006

    COST: 363,764 €

    AREA: 5,050 m2

    DEVELOPER AND AUTHOR:

    Primaria Municipiului Cluj-Napoca

    AUTHORS:

    Tirrena-Garboli